CSM (Quality, Safety and Environment) starts operating in 2006 with the purpose of providing services on a global basis.
CMS S.A. operates in the energy and petrochemical sectors and in oil distillation. The company specializes in Civil Works, Industrial Coating and Scaffolding Rental.
Our satisfied customers are testimony to our technical expertise.
MAIN ACTIVITIES
OUR CLIENTS
PETROQUÍMICA LA PLATA OBRAS CIVILES
CIVIL WORKS
Construction of approximately 400 m of reinforced concrete sleepers and paths including engineering and earthworks.
UGOFE, TEL 3, LESKO S.A.
Project and construction work: electrification of railway lines 1 and 2 between Plaza Constitución, platforms 7 and 8 and Temperly station- Stage 1.1
AXION ENERGY
- Supply and assembly of scaffolds for TK 37.
- Shot blasting and painting of TK 114 Puerto Galván, Bahía Blanca.
- Provision and assembly of scaffolds for boiler 22.
MASA ARGENTINA S.A. / YPF, REFINERÍA LUJÁN DE CUYO
Civil work. Main activities: refurbishment and enlargement of the substation building, auxiliary installations and new infrastructure for the installation of power transformers.
MASA ARGENTINA S.A. / CENTRAL COSTANERA S.A.
New 7600 m² diesel tank N°2, load bearing capacity for tank foundation, diesel equipment, parapet waterproofing, oil separators new civil works, fire prevention systems, construction of new perimeter paths, etc. including earth-moving tasks for the alteration, structure and adaptation of the new tank (TK2) and existing tank (TK1) parapets.
- Construction of access roads, perimeter lighting and railings. Relocation of pedestrian walkway to the rainwater pumps facility of the diesel tank N° 1 parapet,etc.